Solar foundation testing, Ireland
Three days across fields and bog. A stony layer at 1.5–2.5 m shaped a two-size helical-pile design covering ~80 % of the area.
Read case study →Foundations make up 10–15 % of solar CAPEX, and they're usually the line item with the widest variance going into financing. Site-specific test piling tightens that range from ±20–40 % to ±5–10 %, so the figures hold up under bank and investor scrutiny.
Spring 2026 surfaced foundation failures across Nordic solar parks: racks tilted, modules broke, sites that handed over fine last year are being retrofitted at the developer's cost. The fix is below the frost line. Helicasol anchors the helix plate in stable ground year-round and sizes each pile — length, diameter, helix — to the actual soil. The foundation cost you take to the bank still holds when the park is operational.
Foundation = 10–15 % of CAPEX, but it's the first major engineering unknown. Three sub-questions a desk report cannot close. On a €10 M foundation scope, ±20–40 % leaves €2–4 M of variance still on the table when financing closes.
Peat, soft clay, perched water and frost-affected fill can pass a soil survey but still stop a project. The answer only comes from piles in the ground.
Across 100+ ha, ground rarely behaves uniformly. Suppliers with a single product give biased answers. We deliver both helical and rammed C-profile and recommend the one your ground actually wants.
Generic assumptions run ±20–40 % off actual cost. On a €10 M scope that's €2–4 M of uncertainty — enough to make a financial model unfit for bank scrutiny.
Compression, tension and lateral test piles installed on your site. Soil response is read from the piles themselves, not inferred from regional averages.
Pile geometry is sized against measured capacity, then the foundation is priced as a whole. Because the design is built on actual ground response — not regional averages — the budget holds when EPC contracting starts.
Pile geometry, length, helix and spacing chosen for the soil that's actually present. One spec per zone, not one for the whole site.
Eurocode 7, EN 61773 and ICC-ES AC358. The same documentation banks and lenders ask for during due diligence.
Preliminary assessment first, then full test piling on site. The numbers are locked before EPC tendering, not during.
You get measured capacities, named pile counts, a pile-by-pile schedule and a sealed cost range, with every line tracing back to a pile that was actually installed.
Send your site layout, soil data and any structural requirements you have. Engineers review and respond with a preliminary assessment. Free of charge, no commitment.
If the existing data has gaps, we arrange the geotechnical investigations. Optional — only if needed.
Reference piles installed on your ground. Compression, tension and lateral load tests. 50 % of test fees rebated when the project proceeds.
Measured capacity translated into per-pile design, zone-by-zone. Bank-grade documentation, sealed cost range, pile-by-pile schedule.
Site-specific verification across Europe — confirming or refining what the desk study assumed.
Three days across fields and bog. A stony layer at 1.5–2.5 m shaped a two-size helical-pile design covering ~80 % of the area.
Read case study →
Three days on site. Ground from bedrock to soft clay so deep piles sank under their own weight. 58 measurements produced a three-zone foundation strategy.
Read case study →
Reference piling and capacity verification across Eastern and Southern Finland — including peat feasibility and multi-site work supporting investor due diligence.
Formal test report and engineering deliverables compliant with the standards investor due diligence checks against.
Four questions we hear from project developers before financing is locked. If your situation is on the edge of these, ask — we'll tell you straight whether test piling moves the number for you.
Desk reports typically leave foundation scope with a ±20–40 % band. Site-specific test piling tightens that to ±5–10 % — the kind of number a financing committee can defend without a contingency stack on top. On a €10 M foundation scope, that's €2–4 M of variance taken off the table before close.
No. We've test-piled at every stage from feasibility through pre-construction. Earlier is better for budget certainty and for catching a site that needs a different foundation type than the desk study assumed. Later is fine if you only need a final check before financing.
What we'd flag: don't wait until the EPC is on board. The numbers you take to the bank should be your own, not numbers a contractor rounds in their own favour late in the process.
Yes. The data and the engineering report are deliverables you own. Any qualified pile contractor can build to that spec. If you want us to manufacture and install too, the data flows straight into our production and crew schedule with nothing rebuilt.
A desk geotechnical report is ideal. If you only have layout and rough soil type, that's enough to start a conversation. We'll tell you on the first call what's missing for a meaningful preliminary number, and what test-pile programme would close the gap.
Send us project size, location and any soil data you have. You get a preliminary assessment, fully confidential. NDA available on request.